Works Completed at Gosforth Depot

Works Completed at Gosforth Depot

Works Completed at Gosforth Depot Power Supply Projects Ltd as Principal Contractor has recently completed the construction phase for a replacement 11kV rectifier transformer & new 1500V DC by-pass switching arrangement at Gosforth which is now in operational...
PSP Achieves UVDB Accreditation

PSP Achieves UVDB Accreditation

Utilities Vendor Database Verified (UVDB) Following a successful UVDB audit, PSP, with a score of 100% compliance, are fully registered and verified in: Health & Safety, Environment, Quality Management and Corporate Social Responsibility (CSR). Through the...
Design Services

Design Services

Power Supply Projects Consultancy and Design services are provided by a team of highly competent engineers with extensive experience of working in heavy rail, light rail and DNO industries. We have worked on all stages of projects from initial inception through to...
Transport for Greater Manchester

Transport for Greater Manchester

CLIENT: Transport for Greater Manchester LOCATION: Manchester Metrolink DESCRIPTION OF WORKS: TfGM had identified that two new 750V DC traction substations were required on the Altrincham-Bury line in order to enable the operation of back to back double tram services...
Partial Discharge Capabilities

Partial Discharge Capabilities

PSP – Partial Discharge Services Partial Discharge causes progressive brake down of MV/HV insulation where PD activity occurs. PD activity can be present in new installations and can form over time as equipment ages. Partial Discharge is commonly missed during...
NERS Accreditation

NERS Accreditation

Competition in Connections, DNO Contestable Connections & the National Electricity Registration Scheme (NERS) Competition in Connections (CIC) is the term attributed to the opening of the market for the design, procurement and installation of new assets necessary...